Grove Road Stalybridge

Grove Road Stalybridge

All Enquiries Call: 01952 770 990

Grove Road, Stalybridge

Timber Frame commencement date: July 8th 2010

3 Storey apartment block, containing 18 units.

Special Project info:
A) First and second floor joists installed in cassette form for speed of build.
B) Roof trusses pre-assembled on second floor deck, and lifted into place in sections.
B) Total timber frame build programme - 11 days from delivery to sign off.

Day 1 - First delivery. Crane lifting panels.   Ground floor panels half complete.

Ground floor panels complete   Crane lifting cassettes into place

   

   Trusses being assembled and pre-braced on second floor deck

  Trusses pre-assemble and lifted in sections   Day 11 - Structure complete